Overview:

DelDOT is conducting this study through its Transportation Alternatives Program (TAP), which provides funding for projects that improve conditions for walking, rolling, and biking. 

The study will evaluate existing conditions in the study area and develop recommendations and improvement concepts to improve the safety of all road users. 


 

Question title

If you would like to stay informed about the status of this planning process, please provide an email address at which you can be reached:

Project Contact Information

DelDOT Project Manager: Tom Felice

Email: [email protected]

Phone: 855-925-2801   

Project Code (enter when prompted on phone): 6973

Project Milestones

complete
complete
Stakeholder Meeting 1

March 19, 2024

complete
complete
Public Survey 1

April 16–May 15, 2024

complete
complete
Stakeholder Meeting 2

June 18, 2024

complete
complete
Public Open House

August 22, 2024

Drop in any time between 5:00 PM and 7:00 PM

Cab Calloway School of the Arts / Charter School of Wilmington

complete
complete
Public Survey 2

August 22–September 22, 2024

complete
complete
Stakeholder Meeting 3

October 9, 2024

planned
planned
Final Report

Anticipated fall 2024